Skip to content

Utility contractor estimating software

Price pipe by the foot, with the crew and the iron in the number.

A foot of water main is pipe, bedding, a crew, an excavator and a production rate. Price any one of them from memory and the unit price is wrong on every foot. BidDig builds each line from your own rates, then tracks the job against it.

Start free trial

60-day free trial. No credit card required.

Every foot priced from your own rates

Pipe layers, operators and laborers have their own classifications. Excavators, loaders and compaction equipment carry an hourly cost. Pipe, fittings and bedding carry a unit price with the date it was last checked.

More on estimating and bidding
  • Each line item is broken into material, labor, equipment, subcontractor and contingency cost.
  • Equipment is marked as owned or rental, with its own hourly operating cost.
  • Material prices carry the date they were last verified, and you are reminded when one is overdue for a check.
  • Owned and rental equipment are treated differently for tax and bond.
  • Company defaults apply unless a user has their own rates.
  • A project can hold several bids and shows the status of each.
A base bid in BidDig: headers for general conditions, earthwork, utilities and concrete, with line items showing quantity, unit, unit total and total.

How do utility contractors estimate a job?

Line by line, in the unit the owner pays by. Pipe is priced per linear foot, structures and fittings each, bedding and backfill by the ton or cubic yard. Behind each unit price are four costs: the material, the crew, the equipment and how many feet that crew lays in a day.

The production rate is the judgment call, and the rest is arithmetic. Estimating software for utility work should do the arithmetic the same way every time, from rates you have set once, so your attention goes to the production.

Extra work underground

Unmarked utilities, rock and unsuitable material are part of the trade. When the work changes, a change order in BidDig is built like a bid, from the same catalog and the same markup, and added to the project once it has an awarded bid. It can be sent as a proposal and is awarded or rejected on its own, so the extra is priced before it is dug.

Tracking feet against hours

After award, each line item of the bid is a line of the budget. Pipe layers, operators and the excavator are booked to the line they worked on from the timesheet, and material and subcontractor costs are recorded against the same line. A line turns orange from 80% of its budget, which on a pipe run is your signal to compare footage installed with cost spent.

A worked example: 400 LF of 8-inch water main

Say one excavator and a four-person crew lay 100 LF a day. At 8 hours a day, 400 LF is 32 crew hours.

CostHow it is worked outAmount
LaborOperator $38 + two pipe layers at $30 + laborer $24 = $122 an hour x 32 hours$3,904.00
EquipmentExcavator at $85 an hour x 32 hours$2,720.00
Pipe400 LF x $22$8,800.00
Bedding60 TN x $18$1,080.00
Cost before markup$16,504.00 / 400 LF = $41.26 per LF$16,504.00

Every figure here is an example. Your rates, your production and your material prices go in their place, and tax, bond, overhead and profit are applied on top.

Change orders for what the ground hides

Price the extra from the same catalog and markup as the bid, send it as a proposal and record the answer on the project.

More on change orders
  • Change orders can only be added to a project with an awarded bid.
  • The same line item breakdown: material, labor, equipment, subcontractor and contingency.
  • Awarded and rejected changes are both kept on the project.
  • Every proposal style is available for a change order.
A change order for additional dewatering in BidDig, built from an earthwork header and a line item with its quantity, unit and total.

Each pipe run against its budget

Water main, sanitary sewer, storm drain: each line item shows budget vs actual by cost type, with a warning before it goes over.

More on job costing
  • The budget is your estimated cost before markup, so you are comparing cost with cost.
  • No second set of cost codes to keep in step with the estimate.
  • Material, labor, equipment, subcontractor and contingency costs.
  • Hours from the field feed the same job cost.
  • Budget vs actual by cost type and by line item.
  • Orange from 80% of budget, red above 100%.
Budget vs cost by line item in BidDig: total budget and total costs, then a budget bar and cost bar for each header and line item, with one line over budget in red.

What changes when you stop using a spreadsheet for utility contractor estimating.

With a spreadsheetWith BidDig
Unit pricesCarried over from the last bid and adjusted by feelBuilt from crew, equipment and material rates on each line
Pipe and fitting pricesAs old as the spreadsheetA verification date on every material price
ExtrasAgreed on site, argued at the final billA priced change order with its own status
Cost per runKnown at closeoutBudget vs actual per line item during the job

A good fit if

  • You install water, sewer, storm or dry utilities on unit-price bids.
  • You self-perform with your own crews and equipment.
  • Change orders are a regular part of your jobs.

Not the right tool if

  • You need quantities measured from the plans inside the same tool. You enter quantities yourself.
  • You need as-built or inspection records. BidDig tracks cost, not field documentation.

Common questions

Does it come with pipe and fitting prices?

No. Material prices are your own, entered once in the catalog with the date each was last verified. BidDig shows a notice when a price is overdue for checking.

Can I bid by the linear foot?

Yes. LF is a built-in unit, along with CY, SF, SY, TN, HR and LS, and you can add your own, such as EA for structures.

Can I show the owner unit prices but not my cost breakdown?

Yes. The proposal style is chosen when you send. Some styles show item descriptions and prices only, one shows a single lump sum, and others show the full breakdown.

How do I price extra work found during the job?

As a change order on the project. It is built from the same catalog and markup as the bid, can be sent as a proposal, and is awarded or rejected separately from the base bid.

Guides on utility contractor estimating

, 5 min read

How to price a construction change order

A change agreed with a handshake on site becomes an argument at the end of the job. Pricing each change the way you priced the bid, and getting an answer before the work starts, avoids most of it.

, 6 min read

Construction timesheets for job costing

A timesheet that records only the job tells you what payroll will be. One that also records the line item, on the day the work was done, tells you whether the job is making money.

Bid your next job from numbers you can trace.

Set up your catalog, build a bid and send the proposal. Then watch the job against the bid as the costs come in.

Start free trial

60-day free trial. No credit card required.