Skip to content

Concrete estimating software

Concrete is bought by the yard and lost by the hour.

The yards are easy to price. The margin on a concrete job goes in labor: forming, placing and finishing hours that ran past what the bid allowed. BidDig prices labor from your own crew rates and then shows the hours against the bid while the pour schedule can still change.

Start free trial

60-day free trial. No credit card required.

Yards, steel, labor and pump on every line

Each line item is costed as material, labor, equipment, subcontractor and contingency, in CY, SF, LF or your own units, from rates you set once.

More on estimating and bidding
  • Each line item is broken into material, labor, equipment, subcontractor and contingency cost.
  • Equipment is marked as owned or rental, with its own hourly operating cost.
  • Material prices carry the date they were last verified, and you are reminded when one is overdue for a check.
  • Owned and rental equipment are treated differently for tax and bond.
  • Company defaults apply unless a user has their own rates.
  • A project can hold several bids and shows the status of each.
A base bid in BidDig: headers for general conditions, earthwork, utilities and concrete, with line items showing quantity, unit, unit total and total.

How do you estimate a concrete job?

Volume first: area times thickness gives cubic yards, plus an allowance for waste. Then everything the volume does not tell you: forming, reinforcing, placing, finishing, curing and pumping. On flatwork the concrete itself is often the smaller half of the line.

An estimate that prices the yards carefully and the labor by rule of thumb is precise about the wrong thing. The labor needs the same treatment as the material: a crew, a rate and a number of hours on every line.

Labor is where concrete bids go wrong

In BidDig each employee classification, such as finisher, form setter or laborer, has its own rate, and labor is a separate cost on every line item. When the bid is awarded those labor costs become the labor budget for each line.

Hours entered on the timesheet are booked to the line item, so the slab on grade and the footings each show their own labor against budget. A line turns orange from 80% of its budget. If the footings have used most of their labor budget with a third of them still to form, you learn that this week.

Pumping, testing and other hired work

Pump trucks, testing and sawcutting are usually subcontracted. Each line item carries a subcontractor cost alongside material, labor and equipment, so hired work is in the price of the line it belongs to and is tracked there after award.

A worked example: 3,000 SF slab, 4 inches thick

Say 3,000 SF at 4 inches is 3,000 x 0.333 ft / 27 = 37 CY, and you order 39 CY to allow about 5% for waste.

CostHow it is worked outAmount
Concrete39 CY x $165$6,435.00
Wire mesh3,000 SF x $0.35$1,050.00
LaborCrew of five at an average $32 an hour x 16 hours$2,560.00
Pump (subcontractor)One pour, lump sum$900.00
Cost before markup$10,945.00 / 3,000 SF = $3.65 per SF$10,945.00

Every figure here is an example. If the crew takes 22 hours instead of 16, labor is $3,520.00 and the line is $960.00 over before anything else changes.

Forming and finishing hours by line item

The foreman books the crew’s hours to the line they worked on, from a phone browser, and those hours are job cost when they are saved.

More on timesheets and crews
  • Labor hours and equipment hours in one place.
  • Calendar and list views, filtered by employee, project or crew.
  • Entries can be corrected or removed after the fact.
  • Field roles are limited to their assigned projects.
  • Rates and budget vs actual are hidden from field roles.
  • Works in the browser on a phone, with nothing to install.
The Timesheets calendar in BidDig for one month, with employee and equipment hours on each working day and filters for employee, project and crew.

Labor against budget, pour by pour

Budget vs actual by cost type shows labor on its own, and each line item warns you before it goes over.

More on job costing
  • The budget is your estimated cost before markup, so you are comparing cost with cost.
  • No second set of cost codes to keep in step with the estimate.
  • Material, labor, equipment, subcontractor and contingency costs.
  • Hours from the field feed the same job cost.
  • Budget vs actual by cost type and by line item.
  • Orange from 80% of budget, red above 100%.
Budget vs cost by line item in BidDig: total budget and total costs, then a budget bar and cost bar for each header and line item, with one line over budget in red.

What changes when you stop using a spreadsheet for concrete estimating.

With a spreadsheetWith BidDig
Labor on the bidA rate per square foot from memoryCrew classifications and hours on each line
Labor on the jobTotal hours for the week, by personHours booked to the line item they were spent on
Pump and testingRemembered at the end, or notA subcontractor cost on the line
Finding the overrunWhen the job is finishedOrange at 80% of the line’s budget

A good fit if

  • You self-perform flatwork, foundations or site concrete.
  • Labor is the cost you most need to control.
  • A foreman can enter the crew’s hours each day.

Not the right tool if

  • You need rebar detailing or bar lists. BidDig prices reinforcing as a material; it does not detail it.
  • You need volumes calculated from the drawings inside the tool. You enter the quantities.

Common questions

Does it calculate cubic yards for me?

No. You enter the quantity for each line item, in cubic yards or any other unit. BidDig prices it from your rates and tracks cost against it.

Can I track labor separately from material on a pour?

Yes. Budget vs actual is shown by cost type, so labor, material, equipment and subcontractor cost are each compared with their own budget, for the job and for each line item.

Can finishers enter their own time?

Hours are usually entered by the foreman or superintendent, for the people on their crew, against the project and line item. They do not see pay rates or the budget.

How is contingency handled?

Contingency is one of the five costs on every line item, so it is carried where the risk is and tracked as its own cost type after award.

Guides on concrete estimating

, 5 min read

The five cost types in construction job costing

Material, labor, equipment, subcontractor and miscellaneous. What belongs in each, where costs commonly get put in the wrong one, and why it matters for the next bid.

, 5 min read

How to track job costs in construction

Job costing means comparing what a job was bid to cost against what it is actually costing, line by line, while there is still time to do something about it.

Bid your next job from numbers you can trace.

Set up your catalog, build a bid and send the proposal. Then watch the job against the bid as the costs come in.

Start free trial

60-day free trial. No credit card required.