How to calculate labor burden rate in construction

Labor burden rate is annual burden costs divided by annual wages. Here is the formula, what goes into it, and a worked example with every line of arithmetic.

By the BidDig team, , 6 min read

Cover for the post “How to calculate labor burden rate in construction”, showing a BidDig screen.

Labor burden rate is annual burden costs divided by annual wages. Burden costs are what the employer pays on top of wages for hours worked: payroll taxes, workers' compensation, liability insurance priced on payroll, benefits and paid time off. To get a burdened labor rate per hour for bidding, divide wages plus burden by the hours the person actually works.

What is labor burden in construction?

Labor burden is the gap between the wage on the paycheck and what an hour of that person's work costs the company.

The wage is what the employee is paid per hour before deductions.

The burdened labor rate is what the company spends to get one productive hour from that employee. It is the wage plus every cost that exists only because the person is on the payroll.

Bids and job cost should use the burdened rate. The wage is the right number for payroll and the wrong one for almost everything else.

What is included in labor burden?

The components vary by company, by location and by type of work. The usual ones are:

  • Employer payroll taxes. The taxes the company pays on wages, on top of what is withheld from the employee.
  • Workers' compensation insurance. Typically charged as a rate on payroll, and it varies with the classification of work.
  • Liability insurance charged on payroll. If your policy is priced on payroll, that portion follows labor.
  • Benefits. Health coverage, retirement contributions and similar, to the extent the company pays.
  • Paid time not worked. Holidays, vacation and sick days. The company pays for these hours and gets no production from them.
  • Other costs tied to the person. Union fringes where they apply, a phone or vehicle allowance, required training.

What does not belong in labor burden: office rent, the owner's salary, estimating software, the yard. Those are overhead, and they are recovered through the overhead markup. Putting them in both places counts them twice. The post on how to calculate overhead and profit in construction covers that side.

Labor burden rate formula

There are two ways to state it, and they give the same answer.

As a percentage of wages:

  • Labor burden rate = annual burden costs ÷ annual wages for hours worked

As dollars per hour:

  • Burden per hour = annual burden costs ÷ annual hours worked
  • Burdened labor rate = wage + burden per hour

Or, in one step:

  • Burdened labor rate = (annual wages for hours worked + annual burden costs) ÷ annual hours worked

"Hours worked" means productive hours: paid hours less holidays, vacation and sick time. The pay for that time off goes on the burden side.

How do you calculate labor burden rate? A worked example

Every figure below is an example, there to show the method. The tax and insurance rates in particular are made up. Replace each one with your own from your payroll records, your insurance policies and your accountant.

Say an operator is paid $30 an hour and is paid for 40 hours a week all year. Of those paid hours, 120 are holidays and vacation.

Step 1: hours and wages

  • Paid hours: 52 weeks × 40 hours = 2,080
  • Hours worked: 2,080 − 120 = 1,960
  • Gross wages: 2,080 × $30 = $62,400
  • Wages for hours worked: 1,960 × $30 = $58,800

Step 2: annual burden costs

Burden cost Example basis Amount
Paid time off 120 hours × $30 $3,600
Employer payroll taxes Example rate of 8% × $62,400 gross wages $4,992
Workers' compensation Example rate of 10% × $62,400 gross wages $6,240
Health benefits Example of $500 a month × 12 $6,000
Total burden $20,832

Check the sum: 3,600 + 4,992 + 6,240 + 6,000 = $20,832.

Step 3: the burden rate

  • Labor burden rate: $20,832 ÷ $58,800 = 0.354, or 35.4%

Step 4: the burdened labor rate per hour

  • Burden per hour: $20,832 ÷ 1,960 = $10.63
  • Burdened labor rate: $30.00 + $10.63 = $40.63

Check it the other way, from total cost:

  • Total annual cost: $58,800 + $20,832 = $79,632
  • Burdened labor rate: $79,632 ÷ 1,960 = $40.63

And from the percentage: $30.00 × 1.354 = $40.62, the same figure within a cent of rounding.

Why you may see a different percentage for the same person

Some people leave paid time off out of burden and divide by gross wages. With the same example figures:

  • 4,992 + 6,240 + 6,000 = $17,232
  • $17,232 ÷ $62,400 = 0.276, or 27.6%

Nothing about the employee changed. The definition did. That method is fine only if you then divide total cost by hours worked, not paid hours: ($62,400 + $17,232) ÷ 1,960 = $40.63 again. Applying 27.6% to the $30 wage gives $38.28, which leaves the holidays and vacation unpaid for.

How do you use the burdened labor rate in a bid?

Price every labor hour at the burdened rate, not the wage.

Say a job has 500 hours of that operator's time.

  • Labor at the wage: 500 × $30.00 = $15,000
  • Labor at the burdened rate: 500 × $40.63 = $20,315
  • Difference: $20,315 − $15,000 = $5,315

In this example, a bid priced at the wage leaves $5,315 of real labor cost uncovered before any markup is applied. The crew can work exactly 500 hours, the job cost report can show labor on budget, and the company still paid that $5,315 out of profit. Overhead and profit worked out as a percentage of cost then start from a base that is too low.

Use the same rate in job cost as in the bid, or the comparison stops meaning anything:

  • Burdened in the bid, wage in job cost. Every job appears to beat its labor budget. Real overruns stay hidden.
  • Wage in the bid, burdened in job cost. Every job appears to run over on labor from the first day, and the report gets ignored.
  • Burdened in both. An hour bid and an hour worked cost the same, so a variance means the crew used more or fewer hours than planned.

Common mistakes when calculating labor burden

  • Dividing by paid hours. The pay for holidays and vacation has to be carried by the hours when the person is working, because those are the only hours a job can be charged for.
  • One percentage for the whole company. An operator and a laborer have different wages and may have different insurance rates. Build a rate per classification.
  • Putting overhead in burden. If it would still be paid with that employee gone, it is overhead.
  • Ignoring overtime. The premium portion of overtime raises the cost of the hour. Some burden components apply to it and some may not. Ask your accountant, then be consistent.
  • Never updating it. A new insurance rate or a raise changes the burdened rate the day it takes effect. Review once a year, and when something changes.

How BidDig handles labor rates

BidDig bids are built from your own catalog, including employee classifications, and each line item is costed as material, labor, equipment, subcontractor and contingency. The awarded bid's line items become the budget, and hours entered on timesheets against a line item are job cost when saved. Work out your burdened rates first and use them on both sides, so the labor budget and the labor cost are measured the same way.

See estimating and bidding, and hourly and salaried staff in job costing for people who are not paid by the hour. For how the pieces fit together, see construction estimating software. If you are starting from scratch, read how to bid a construction job, step by step.

Budget vs cost by cost type in BidDig: materials, employees, equipment, sub companies and contingencies, each with budget, cost and percentage used.
In BidDig. Budget against cost by cost type.

Keep reading

, 5 min read

Why spreadsheet construction estimates go wrong

Spreadsheet estimates go wrong because the costs live inside each job file. Copy the file and old rates, broken formulas and one-off adjustments come along unnoticed.

, 6 min read

How to structure a construction crew

A crew is a set of people and machines that work together under one foreman. Keeping that set stable is what lets you compare one job's costs with the next.