How to calculate overhead and profit in a construction bid
Overhead and profit are two different numbers that do two different jobs. Here is how to find your overhead rate from a year of figures, set a profit rate, and apply both to a bid.
By the BidDig team, , 6 min read

To calculate overhead and profit in a construction bid, divide a year of overhead costs by the direct job cost you expect to perform in that year. That gives your overhead rate. Multiply the bid's direct cost by that rate, add the result, then multiply the new subtotal by your profit rate. Keep the two rates separate.
Here is why that matters. You finish pricing a job, and material, labor, equipment and subs add up to $200,000. You add "20 percent" on top and send it. Sometimes the 20 is 15 because you want the job. One number is doing two jobs, and nobody can say afterwards which part paid for the office and which part was meant to be left over.
What is the difference between overhead and profit?
Overhead is what it costs to be in business whether or not a particular job happens. None of it shows up in a line item, but every job has to carry a share of it.
Profit is what remains after the job's direct costs and its share of overhead are paid. It is the return for taking the risk, and it funds growth, equipment purchases and the bad year.
If you combine them into one markup, you cannot tell whether a "discount" came out of profit or pushed the job below what it costs you to exist.
What counts as overhead in a construction company?
Overhead is every cost you cannot charge to a specific job. Typical items:
- Office rent, utilities, phones and software
- The owner's salary and office staff
- The estimator's salary
- Insurance that is not tied to a job
- Accounting and legal fees
- The yard, and the pickup that is not charged to any project
Costs that belong to one job are not overhead, even when they feel like it. A superintendent on one site, a site trailer and mobilization are direct costs. Give them their own line items in the bid. If they are counted in overhead as well, the job pays for them twice. If they are in neither, it does not pay for them at all.
How do you calculate your overhead rate?
Overhead is a real cost, so the rate should come from your books, not from habit.
Overhead rate = annual overhead / annual direct job cost
- Add up a year of overhead costs from your accounts.
- Add up the direct job cost (material, labor, equipment, subs) you expect to perform in the same year.
- Divide the first by the second.
Here is an example. The figures are made up to show the arithmetic.
| Annual figure | Amount |
|---|---|
| Office, yard, phones and software | $70,000 |
| Owner and office salaries | $210,000 |
| Insurance not tied to a job | $50,000 |
| Accounting, legal and other | $30,000 |
| Total overhead | $360,000 |
| Expected direct job cost | $3,000,000 |
The overhead rate is 360,000 / 3,000,000 = 0.12, or 12 percent of direct cost.
Two things follow from that sum. If volume falls and overhead does not, the rate you need goes up: the same $360,000 over $2,400,000 of direct cost is 360,000 / 2,400,000 = 15 percent. And a job priced with less than its share of overhead is not covering its place in the company, however good the profit line looks.
Rework the rate at least once a year, and again when volume or overhead changes noticeably.
How much profit should you add to a construction bid?
There is no correct percentage to copy from somebody else. Profit is a decision, and the clearest way to make it is the same way as overhead: start from a yearly figure and turn it into a rate.
Decide what the business needs to earn in the year, after overhead, to pay for equipment, carry slow months and reward the risk. Then divide by the cost that profit will be applied to.
Using the same example, say the target is $268,800. Direct cost plus overhead is 3,000,000 + 360,000 = $3,360,000. The profit rate is 268,800 / 3,360,000 = 0.08, or 8 percent of cost including overhead.
You can move the profit rate up or down on a single bid for the risk of the job, the customer or the competition. That is a judgment. The overhead rate is not, because the office costs the same either way.
How do you apply overhead and profit to a bid?
Take the $200,000 job and apply the two rates as separate steps, overhead first.
| Step | Calculation | Amount |
|---|---|---|
| Direct cost | $200,000 | |
| Overhead at 12% | 200,000 x 0.12 | $24,000 |
| Cost with overhead | 200,000 + 24,000 | $224,000 |
| Profit at 8% | 224,000 x 0.08 | $17,920 |
| Price before tax and bond | 224,000 + 17,920 | $241,920 |
The order matters. If you add the two rates together and apply 20 percent to direct cost, you get 200,000 x 1.20 = $240,000. The $1,920 difference is the profit on the overhead: 24,000 x 0.08 = $1,920. Neither method is wrong, but the profit rate above was worked out on cost including overhead, so it has to be applied that way.
Apply the rates the same way on every bid
A rate that is slightly off but applied the same way every time can be corrected. You look at a year of finished jobs, see that you came up short, and adjust. A rate that changes from bid to bid cannot be corrected, because there is nothing steady to compare against. Typical ways it drifts:
- One estimator marks up material and labor, another marks up everything including subs.
- The rate is typed over in a spreadsheet cell to win a job and never changed back.
- Tax and bond are added before markup on some bids and after on others.
Decide the rates and the order once, write them down, and make a change on a single bid a deliberate decision that somebody can see.
Is the overhead rate a percentage of cost or of revenue?
It can be either, and mixing the two is an easy way to come up short.
The 12 percent above is overhead as a share of direct cost, because that is the number a bid starts from. Your accountant is more likely to quote overhead as a share of revenue. In the example, revenue for the year is 3,000,000 + 360,000 + 268,800 = $3,628,800, so overhead is 360,000 / 3,628,800 = 9.9 percent of revenue.
Both figures describe the same $360,000. But if you take the 9.9 percent and add it to direct cost, you recover 3,000,000 x 0.099 = $297,000 and finish the year $63,000 short of your overhead without ever seeing a bad number on a bid.
This is the same trap as confusing markup with margin. The difference between the two, the formulas for converting one to the other and a conversion table are in markup vs margin in construction.
How BidDig handles overhead and profit
In BidDig, tax, bond, overhead and profit are calculated from default rates. The company sets its defaults, a user can have their own defaults, and the rates can be changed on an individual bid when a job calls for it. Each line item is costed first as material, labor, equipment, subcontractor and contingency, so the markup is applied to a cost you can see. Read more on the estimating and bidding page, or continue with what belongs in a bid line item and how much contingency to carry in a bid. For how the pieces fit together, see construction estimating software. If you are starting from scratch, read how to bid a construction job, step by step.